New Elementary School Construction Updates
The Board of School Trustees previously approved the replacement of Carmel Elementary School with a new facility on the same site and a new elementary school facility at the Clay Center Road site.
This web page will be used to keep the community updated on the planning and progress of these two elementary schools. Both of these schools are expected to be open at the start of the 2021-2022 school year.
Timeline for New Elementary Schools
- Programming October 2018-December 2018
- Schematic Design January 2018-April 2019
- Design Development May 2019-July 2019
- Construction Documents August 2019-October 2019
- Bidding November 2019
- Construction December 2019-October 2021
- Commissioning/Move-In May 2021-June 2021
- Schools Open for the 2021-2022 School Year